Edgware Road Footbridge
Overview
- Contract name:
- Edgware Road Footbridge
- Client:
- Transport for London
- Duration period:
- 4 Months
- Form of contract:
- Design & Build
- Value:
- £600,000
- Type of work:
- Infrastructure Maintenance
The project involved the design and build of a new footbridge over the railway tracks linking the 1st floor of Griffiths House to island platform 4. Prior to the installation, the exisiting bridge was demolished and removed during a weekend possession. A 300T crane was used to lift the new bridge into position.